Old toilet area, which sits nicely right next to window, on the right is shower wall
Shower side walls being demolished
Looking in from bedroom after almost all interior studs removed
Old closet walls removed
Shower walls removed
Old vanity
Shower demolition, only pan remains
Looking to bedroom after almost all interior studs removed
Vanity removed
All the various tile flooring in the bathroom. The aqua square tiles were underneath the vanity and match the countertop. The large off-white ones were in the space between the two vanities.
Wood that helped for base of shower was rotting
All that is left of the shower pan
Bathroom ceiling and insulation removed
The now larger area minus drywall and insulation
Bathroom after removal of everything but flooring
Old closet area after drywall and insulation removal
Exterior wall looking towards bedroom
View from bedroom door, hole in subfloor and pipes show where shower used to be
View from bedroom door, pipes show where vanity used to be
View from exterior corner, WC to left
Plumbing and electrical rough-ins done
Plumbing rough-ins done in shower area
Plumbing and electrical rough-ins done in toilet area
Plumbing and electrical rough-ins done in vanity area
Insulation complete
Insulation complete in shower area. Foil backed foam used behind pipes.
Insulation complete in toilet area
Door to water closet framed
Shower frame built and water proofed
Tub platform built
Radiant heat installed down walkway but not where vanity will be on right.
Radiant heat installed down walkway. Tub and shower liner have been installed.
Radiant heat installed down walkway but not where toilet will be.
Radiant heat installed down walkway.
Drywall in place with holes for medicine cabinets’
love home renovation and latin america, too. impressed by all your hardwork, both with houses and with weight loss and exercise. thamks for the inspiration. –Amy
Pingback: Home Renovation Phase 3 Demolition Begins | Geeky Girl Engineer
Pingback: Master Bathroom Demolition Continues | Geeky Girl Engineer
Pingback: Phase 3 Deconstruction Continues | Geeky Girl Engineer
Pingback: Master Bathroom Reconstruction Begins | Geeky Girl Engineer
love home renovation and latin america, too. impressed by all your hardwork, both with houses and with weight loss and exercise. thamks for the inspiration. –Amy